Case Study School Classrooms LED Upgrade

School Hall LED lighting

The Hawthorns, Bletchingley

Organisation Type
Independent Primary School
Project Type
Phased install across the whole school

Project Scope

  • A phased install across many areas as and when the priority dictates
  • Upgrading to LED lighting in classrooms, halls, the kitchen & dinning area, corridors and external buildings
  • Installation of new emergency lighting during upgrades
  • Verification of savings via before and after energy measurement

Outcomes

  • 64% Reduction in lighting energy consumption
  • Phase approach to meet budgets and upgrade constraints
  • Increased levels of lighting in all areas
  • 5 year warranty on the fittings